The correct time to discuss visible finishes for wall plates, surface mount
speakers, and wall mounted screen casings is during the:

a. Ordering
b. Installation
c. Site survey
d. Contract award

What do you think is the best answer? 

Post your choice below for a chance to win a $25 Amazon gift card!

Check back Friday to see if you got it right.

UPDATE: The correct answer is....

c. Site survey

Watch your inbox to see if you won a gift card!

Please sign in

If you are a registered user on AVIXA Xchange, please sign in

Go to the profile of Ashokkumar Baskaran
over 1 year ago

d. Contract award

Go to the profile of Nicole Abou Rjeily
over 1 year ago

a

Go to the profile of Nicole Abou Rjeily
over 1 year ago

site survey

Go to the profile of Franklin Frisby
over 1 year ago

C. Site Survey

Go to the profile of Wayne Rorex
over 1 year ago

C. Site Survey is my answer (also because C is for cookie and that's good enough for me)

Go to the profile of Marco Buitenhuis, CTS
over 1 year ago

C. site survey

Go to the profile of Rob Orrell
over 1 year ago

Site Survey.

I am enjoying these questions but it would be good to see the originator posting the correct answer at the end of the week?

Go to the profile of Rob Orrell
over 1 year ago

sorry just noticed the friday line and the answer on last weeks.... d'oh!! 😁

Go to the profile of IGNASI SANAS MARTIN
over 1 year ago

c. Site survey

Go to the profile of Tim Dickson
over 1 year ago

d. Contract award

Go to the profile of Jonathan Wunrow
over 1 year ago

C. Site survey

Go to the profile of Jose Mozota
over 1 year ago

c site survey

The words "visible finishes" can be misleadings as you may think that you do not know the color of the plate you will need and decide to choose a later stage in the process.  I think it means that the elements will be visible and that directs you towards the kind of  "visible" elements you will need

Go to the profile of Mark Obey
over 1 year ago

c

Go to the profile of Nicholas Graybeal
over 1 year ago

Site survey. 
mat this point you have eyes on the project in a way that you may not in other stages of the process.

Go to the profile of Joel Hagen
over 1 year ago

Site Survey

Go to the profile of Michael Leach
over 1 year ago

c. Site survey

Go to the profile of kabeer hajireen
over 1 year ago

Ordering 

Go to the profile of Kathryn Gaskell
over 1 year ago

C. Site Survey

Go to the profile of Jim Griffith
over 1 year ago

D. The sooner the better, especially with long lead items like projection screens.

Go to the profile of Jean-Marc Dubois
over 1 year ago

d - Contract award

Go to the profile of SONG HEUNG SHIK
over 1 year ago

c. site survey

Go to the profile of Logan Evans, CTS, MTA-C
over 1 year ago

C Site survey

Probably follow up and verify before ordering though

Go to the profile of Jason Ramirez
over 1 year ago

C

Go to the profile of Hannah Zelmanski
over 1 year ago

Happy Friday!

The correct answer is:

c. Site survey

Watch your inbox to see if you won a gift card!

Go to the profile of Mayssam Takfallah
over 1 year ago

C

Go to the profile of Aneesh kumaran
over 1 year ago

c

Go to the profile of Barry Sato
over 1 year ago

Depending on the mind frame of the client it could be earlier in the cycle, but in reality I find their attention and readiness to give a final answer to finish options after contract and at time of ordering.