CTS Sample Question of the Week: March 17, 2025

After a new multi-room AV integration project, an owner should expect what of following in the “close out” documentation package?
a. Request for information form for proposed equipment substitution needed to replace originally specified
b. Change order approval request form for all substituted pieces of equipment
c. As built drawings that include final specifics (makes/model/etc.) of all equipment installed
d. Notes from all on-site construction coordination meetings
Which do you think is the best answer? Post your choice below and check back Friday to see if you got it right.
Update: The correct answer is - c. As built drawings that include final specifics (makes/model/etc.) of all equipment installed
Thanks to everyone who participated in this week's question! Come back next week for another one.
Try the newly updated CTS Sample Questions on avixa.org. They are free for anyone to take.
Please sign in
If you are a registered user on AVIXA Xchange, please sign in
c. As-built drawings that include final specifics (makes/model/etc.) of all equipment installed
Basically C, but is important D as a history of the project.
c. As built drawings that include final specifics (makes/model/etc.) of all equipment installed
C, This helps the owner to know exactly what they have for future reference and for support calls if needed.
C.
C
c. As built drawings that include final specifics (makes/model/etc.) of all equipment installed
C
C
C
c. As built drawings that include final specifics (makes/model/etc.) of all equipment installed
C
c. As built drawings that include final specifics (makes/model/etc.) of all equipment installed
c
c. As built drawings that include final specifics (makes/model/etc.) of all equipment installed
C
C
C