Which phase comes first in a project?

a. Commissioning and Training Phase
b. The Design Phase
c. The Program Phase
d. The Construction Phase

Which do you think is the best answer? Post your choice below and check back Friday to see if you got it right.

Update:

The correct answer is: c. The Program Phase