When conducting a site survey at an active construction site what should you confirm FIRST before arriving onsite?
a. The number of network drops you'll need for each conference room.
b. Required PPE to be onsite.
c. Condition of the carpets.
d. The color of the walls.
Which do you think is the best answer? Post your choice below and check back Friday to see if you got it right.
Update:
The correct answer is - b. Required PPE to be onsite.
Thanks to everyone who participated in this week's question! Come back next week for another.
CTS Sample Question of the Week: July 29, 2024
Every week we're going to post a question from the CTS Sample Question set. Check back weekly for new questions.
Like
Be the first to like this
Please sign in
If you are a registered user on AVIXA Xchange, please sign in
b
b
b. Required PPE to be onsite.
b. Required PPE to be onsite.
b. Required PPE to be onsite.
Confirming the required personal protective equipment (PPE)
B
b
b
BBB
B
b. Required PPE to be onsite.
B
Answer is b
b
b. Required PPE to be onsite.
b. Required PPE to be onsite.
a. The number of network drops you'll need for each conference room.
b
B.
B
b. Required PPE to be onsite.