What does a Work Breakdown Structure (WBS) address?
a. Products and services as they relate to work done on a project
b. A list of required personnel
c. What specific work will be done including timing and lunch breaks
d. How much of a certain item should be ordered to keep the project on track
Update:
The correct answer is - a. Products and services as they relate to work done on a project
Thanks to everyone who participated this week (and this year)! See you in 2025.
In the meantime, try the newly updated CTS Sample Questions on avixa.org. They are free for anyone to take.
Please sign in
If you are a registered user on AVIXA Xchange, please sign in
c
A
C
A
A
A
a. Products and services as they relate to work done on a project
A
A
A
A. I never included lunch breaks in my WBS's, only coffee breaks :)
A
c. What specific work will be done including timing and lunch breaks
a. Products and services as they relate to work done on a project
A
a. Products and services as they relate to work done on a project