Which phase of an AV project comes immediately AFTER the Program Phase?

a. The Design Phase
b. Project Planning and Coordination Phase
c. The Verification Phase
d. The Documentation Phase

What do you think is the best answer? Post your choice below and check back Friday to see if you got it right.

Update:

The correct answer is - a. The Design Phase

Thanks to everyone who participated in this week's question! Come back on Monday for another.

Please sign in

If you are a registered user on AVIXA Xchange, please sign in

Go to the profile of Franklyn Mogale
3 months ago

A. The Design Phase

Go to the profile of Kevin Paul Magracia
3 months ago

A.

Go to the profile of Shaikh Abdul Sattar
3 months ago

a. The Design Phase

Go to the profile of Daniel Braun
3 months ago

a

Go to the profile of Harish040
3 months ago

a. The Design Phase

Go to the profile of Josh Salinas
3 months ago

A

Go to the profile of Aarom Meador
3 months ago

A

Go to the profile of Jheel rathod
3 months ago

a. The Design Phase

Go to the profile of Sergio Torrano Díaz
3 months ago

a. The Design Phase

Go to the profile of Trevor Harris
3 months ago

A

Go to the profile of Jonathan Wunrow
3 months ago

a. The Design Phase

Go to the profile of Rachel Gaughan
3 months ago

A

Go to the profile of Earl Gorden
3 months ago

c. The Verification Phase

Go to the profile of Pierre Leduc
3 months ago

a

Go to the profile of Barry Sato
3 months ago

Ayyyy (in the Fonz's voice)

Go to the profile of Racheal Aye
3 months ago

A

A